Ringsted 12+2MW Straw-Fired Plant: Delivering Overcapacity and Reliability

Runarsson A/S delivered a 12+2MW plant for Ringsted Forsyning’s heating plant in Benløse. The plant is engineered with 20% overcapacity, enabling a total output exceeding 14MW. As with previous projects, Runarsson A/S was responsible for the core components, including the complete feeding system with bale shredder, grate and boiler, flue gas cleaning system, ash handling system, and all supporting structures such as access routes and galleries. The plant was delivered on time and within budget, with operational start-up achieved less than a year after groundbreaking. The plant continues to perform exceptionally well, and Runarsson A/S remains a dedicated long-term service partner. Video courtesy of Ringsted Forsyning.