A year ago we started conversations with SWS A / S on the design, manufacture and assembly of a rotary oven, as well as a feeder for their hazardous waste incinerator facility, burning medical and chemical waste.
In March of this year we signed a contract in which we declared the date 2.10.2017 as the date of putting both devices into use.
We met the deadline. Today after a two-month, successful trial period, SWS accepted our products and we formally handed it over.
Our oven works impeccably. With the new oven, the capacity has been increased by 40%, and down-time will be reduced by 1 week. The working conditions of people operating the incineration plant have also improved.
Oven was affectionately named by operators Fat Berta.
So we introduce our Berta to her new home J